Hamley Bridge, South Australia

Project Description

Fleurieu Civil & Construction were engaged by SA Water to install 981m of DN300 DICL in Hamley Bridge.

The project included the development of a new service road and the management of local vegetation through thorough environmental considerations.

The construction included:

  • 981m of DN300 DICL pipe (ductil iron cement lined)

  • 48m of DN100 DICL

  • Installation of 3 stop valve assemblies

  • 6 x stop valve assemblies

  • 3 x fire plugs

  • Reinstatement of roads

  • Full system flush, chlorination, and commissioning

The project was executed on time, on budget, and with zero safety events. A great achievement by the team working in a remote environment.

Previous
Previous

Winninowie

Next
Next

Koonnibba